GJ19- Equity change after cutback- for prior month

9  comments

GJ19- prior period equity change

GJ19 is similar to GJEC, but GJ19 is run for equity changes for the prior period. E.g. if there was a $100 charge and the equity share was 60/25/15 and there were postings in month 3 with this equity group.

Cutback has also been run i.e. we billed the partners based on the old equity group share.

GJ19 is for postings of the previous months.

This will reverse the old cutback entries and book them to the new partners based on the working interest in the new equity group.

 

Screen above shows the old equity group that is linked to equity group 2.

The screen below shows the vendor posting of $100.

 

The cutback screen below shows that it was billed in the ratio of 60/25/15 i.e. the working interest of the old equity group.

 

The new equity group has the working interest as 50/25/25. 

 

 The original posting’s document
date was 3/5/2018 and the new equity group is active is of 3/3/2018, so this posting should be adjusted to equity group 2. 

 

Run the tcode GJ19 or access through the menu path below. 

 

Enter the following

1- Company code for which you are running equity change.

2- Enter a venture if you are restricting it to a venture. 

3- Enter the old and new equity group.

4- Enter the date range that the program should consider. 

and enter the posting details.

 

Click on execute and see if you get any errors.

 

Click on the spools to view the details. 

The bottom half will show you the current cutback share. 

 

and then you see the new equity share

 

go back and remove the test run.

 

You might see a message

 

There should be no errors. 

 

View the documents that were posted. 

The first document is the reversal of the cutback that was done to the original equity group.

 

and then there is the new cutback with the new equity group.

 

The posting was done to the new equity share of 50/25/25.

Let us know if you have any questions by leaving a comment below. If you want to learn more about JVA, head over to the main jva page


You may also like

F-90 Acquisition from vendor

F-90 Overview– This tcode is used to purchase an asset directly. This allows for the asset to be capitalized on purchase. This is very rare. Usually, the asset purchase goes through the PO process and the asset shell is created first and then the values are added to it. E.g. if you are purchasing a

Read More

AJRW and AJAB-Asset Fiscal year change

This guide goes over the year end closing steps of Asset Accounting. Overview of AJAB Asset year end close– You use the year-end closing program to close the fiscal year for one or more company codes from an accounting perspective. Once the fiscal year is closed, you can no longer post or change values within

Read More

Subscribe to newsletter!